First, strobe installment matters needing attention
1st, before the strobe installment, first inspects each connection spot the bolt because whether in transportation loading and unloading to create becoming less crowded, if has becomes less crowded should perform to fasten.
2nd, inspects the host to set up the frame and the horizontal frame links on to stop the water surface whether to have the dislocation, if will have the dislocation to become less crowded the connecting bolt to stop the water surface adjustment in the identical plane.
3rd, the strobe installs when should use the whole to take place the installment, forbids the floodgate frame, the damper plate fission installment, prevents the floodgate frame distortion.
4th, around two phase of constructions, takes place the strobe integral hoisting, finds, about correct position, then the adjustable bolt and the project match the steel bar to weld reliably.
5th, before strobe leaving the plant, to cause the damper plate, the floodgate frame fitting to be tighter, after the installment, reduces the gap, 2 meters above strobes have installed the clamp card iron on the high and low horizontal frame, set up in frame's slanting iron to increase the set screw. Attention after gap adjustment in the card iron and the slanting iron's set screw demolition, causes the strobe to open shuts.
6th, when concrete, flows in the damper plate, in the floodgate frame, slanting hard, the back plate gap mortar to eliminate, prevents the setting of mortar influence to open shuts.
Second, gate installment matters needing attention
Screw rod type gate:
1st, installs when the foundation ground should reliable smooth, leaves leeway foundation bolt's position, after the gate arriving, levels the irrigation formation.
2nd, gate's lead screw must be parallel to the strobe attrition track surface, simultaneously is vertical in hangs the trunnion, double hangs the type two seat-ss on a plane to in the identical plane, two lead screws parallel, simultaneously is vertical in hangs the trunnion, hand operated or charged gate, hand operated high and low starts first several times, after achieving the standard, only then charged uses; When charged operation, is equipped with the drop depth controller, but the operators do not leave the location arbitrarily, by against because of breakdowns and so on electric circuit, creates collision accident's occurrence.
Third, QPQ/QPK hoists the type gate:
1st, installs when the foundation ground should reliable smooth, leaves leeway foundation bolt's position, after the gate arriving, levels the irrigation formation.
2nd, circles the first steel wire on the balance wheel, the rope long nearby two divides equally, circles through the movable pulley group the steel wire, simultaneously fixes the both sides in the reel nose.